In order to reduce and eliminate water wastage in the urban water distribution network, as well as the reconstruction of the old water distribution network and replacement of existing pipes with ductile iron pipes, Arun Ab Company as a project contractor with records from 10/17/2009 with number The contract 9664/14109 has started working and so far, due to the leading problems, it has been able to progress in accordance with the provisions of the contract.
Contract amount 88,892,377,324 Rials: The amount of the last approved status statement (temporary number 4) 30,964,813,008 Rials
13,500 meters of piping according to the contract: about 7,000 meters of piping has been done
2300 branches in the reconstruction area according to the contract: about 600 branches have been done